What does a new bathroom cost, and how long does it take?

TF Heating logo TF Heating 12 September 2026 4 min read

The cost of a bathroom is driven by whether the layout moves, how many trades are involved, and what you choose to put in it. Keeping the toilet and waste where they are is the single biggest saving. Most of the calendar goes on trades and deliveries, not on the plumbing days.

We do the plumbing side of bathrooms, so this is written from that end: what makes the plumbing bigger or smaller, and what order the whole job has to run in. Tiling, plastering and electrics are separate trades.

What makes it cost more

  1. 1

    Moving the toilet

    The waste has to fall the right way to reach the soil pipe. Move the toilet and you are often into floor work or boxing in. Keeping it where it is is the biggest single saving available.

  2. 2

    Changing the layout

    Swapping a bath for a big shower enclosure, or moving the basin across the room, means new hot, cold and waste runs in walls and floors.

  3. 3

    What you pick

    The suite, the shower and the taps can vary by a lot for the same installed job. This is the part you control most.

  4. 4

    What is behind the old one

    Nobody knows until the rip out. Old lead or steel pipework, rotten floorboards and previous bodged work are the usual surprises, and any honest quote allows for the possibility rather than pretending it cannot happen.

The order it has to happen in

This is what people wish they had known, because it explains why a bathroom takes a fortnight when the plumbing is a few days.

  • Rip out, then first fix plumbing and any electrics in the walls
  • Plastering or boarding
  • Tiling
  • Second fix plumbing: suite, taps, shower, towel rail, all connected and tested
  • Silicone, final checks and the bits everyone forgets

Skip an order and something has to come back out. The waiting between stages, and waiting on parts that were ordered late, is where bathrooms actually lose time.

How to keep it under control

  • Get the plumbing looked at before you order the suite
  • Keep the toilet where it is if the budget is tight
  • Have everything on site before the rip out starts
  • Agree who is doing tiling and electrics before day one, not during

Need this doing?

Bathroom Plumbing & Fitting in Telford

Showers, baths, basins and full bathroom plumbing

Related questions

How long does a bathroom refit take?
The plumbing is usually a few days spread across the job. The overall length depends on the other trades and on parts arriving. Anyone giving you a finish date before the rip out has not seen behind your walls.
Do you supply the bathroom suite?
Most people buy their own suite, which gives you the choice and the control. We are happy to tell you what will and will not work with your pipework and pressure before you order.
Can I keep my bath and add a shower over it?
Usually the cheapest way to get a shower, yes. Whether it will be a good shower depends on what feeds it, which is worth checking first.